what is the 100% rule in the context of wbs? making sure that each team member is 100% productive ensuring…

what is the 100% rule in the context of wbs? making sure that each team member is 100% productive ensuring that the project is completed 100% on time ensuring that the project budget is not exceeded by more than 100% ensuring that 100% of the project scope is identified and captured in the deliverables
Answer
Brief Explanations:
The 100% Rule in Work - Breakdown Structure (WBS) ensures that all of the project scope is identified and captured in the WBS deliverables. It's about comprehensively covering the scope, not about individual performance, time - completion, or budget - control in the strict sense.
Answer:
Ensuring that 100% of the project scope is identified and captured in the deliverables