the development methodology where each part of a project is done in order after each other is called: agile…

the development methodology where each part of a project is done in order after each other is called: agile waterfall scrum none of the above

the development methodology where each part of a project is done in order after each other is called: agile waterfall scrum none of the above

Answer

Answer:

B. Waterfall

Brief Explanations:

In waterfall methodology, project - phases are sequential, with each part done after the previous one. Agile and Scrum are iterative and incremental, not strictly sequential like waterfall.