a ____ ____ is a document that is developed over the course of the project. it is a summation of the risks…

a ____ ____ is a document that is developed over the course of the project. it is a summation of the risks specific to the project and the overall project risk level.\n\nfault report\nrisk report\ni dont know\nrun report
Answer
Brief Explanations:
A risk report details project - specific risks and overall risk level, developed during the project. A fault report focuses on errors or malfunctions, and a run report is not related to risk summation.
Answer:
B. risk report