below is an example of a ____ chart for a doll manufacturer, which is a tool used by project managers to…

below is an example of a ____ chart for a doll manufacturer, which is a tool used by project managers to track the status of a project and predict a timeline.\n\nmachine a (heads molded)\nmachine b (bodies molded)\nmachine c (fabric cut)\nmachine d (clothing sewn)\nline a (assembly)\nline b (painting)\n\n□ = completed work\n■ = work to be done\n\noptimization\ngantt\nproject strategy\npert
Answer
Brief Explanations:
Gantt charts are used by project managers to track project - status and predict timelines. They display tasks against time, showing start and end dates, and progress. The given chart has tasks on the y - axis and weeks on the x - axis, with completed and remaining work indicated, which is characteristic of a Gantt chart.
Answer:
B. Gantt