going to market - basics math quiz\nquestion 2 of 10: your go - to - market strategy calls for a slick…

going to market - basics math quiz\nquestion 2 of 10: your go - to - market strategy calls for a slick website. you estimate 10 hours of programming and 5 hours of design. programmers bill at $85/hr and designers get $65/hr. how much will your new site cost?\n a) $1,175\n b) $1,375\n c) $1,525\n d) $1,605

going to market - basics math quiz\nquestion 2 of 10: your go - to - market strategy calls for a slick website. you estimate 10 hours of programming and 5 hours of design. programmers bill at $85/hr and designers get $65/hr. how much will your new site cost?\n a) $1,175\n b) $1,375\n c) $1,525\n d) $1,605

Answer

Explanation:

Step1: Calculate programming cost

$10\times85 = 850$

Step2: Calculate design cost

$5\times65=325$

Step3: Calculate total cost

$850 + 325=1175$

Answer:

A. $1,175$