move each change management process step from the list on the left to the scenario that describes it on the…

move each change management process step from the list on the left to the scenario that describes it on the right.\nchange management process steps (not in order)\napprove the change\nassess the change impact\nidentify the change\nimplement the approved change\nscenarios\nyou request a cost estimate for 15 gallons of paint.\n15 gallons of paint are delivered to the construction site.\nthe sponsor tells the purchasing manager to buy 15 gallons of additional paint.\nthe construction manager informs you that the team will need an additional 15 gallons of paint.

move each change management process step from the list on the left to the scenario that describes it on the right.\nchange management process steps (not in order)\napprove the change\nassess the change impact\nidentify the change\nimplement the approved change\nscenarios\nyou request a cost estimate for 15 gallons of paint.\n15 gallons of paint are delivered to the construction site.\nthe sponsor tells the purchasing manager to buy 15 gallons of additional paint.\nthe construction manager informs you that the team will need an additional 15 gallons of paint.

Answer

Brief Explanations:

  • "You request a cost estimate for 15 gallons of paint." - Esto es assess the change impact, ya que se está evaluando el impacto financiero del cambio (necesitar 15 galones de pintura).
  • "15 gallons of paint are delivered to the construction site." - Esto es implement the approved change, ya que se está llevando a cabo la acción de suministrar la pintura aprobada.
  • "The sponsor tells the purchasing manager to buy 15 gallons of additional paint." - Esto es approve the change, ya que el sponsor está dando el visto bueno para la compra.
  • "The construction manager informs you that the team will need an additional 15 gallons of paint." - Esto es identify the change, ya que se ha detectado la necesidad de un cambio (más pintura).

Answer:

  • You request a cost estimate for 15 gallons of paint: Assess the change impact
  • 15 gallons of paint are delivered to the construction site: Implement the approved change
  • The sponsor tells the purchasing manager to buy 15 gallons of additional paint: Approve the change
  • The construction manager informs you that the team will need an additional 15 gallons of paint: Identify the change