a packaging employee making $20 per hour can package 16 items during that hour. the direct material cost is…

a packaging employee making $20 per hour can package 16 items during that hour. the direct material cost is $0.90 per item. what is the total direct cost of 1 item?
Answer
Explanation:
Step1: Calculate labor cost per item
$20\div16 = 1.25$
Step2: Calculate total direct - cost per item
$1.25+0.90=2.15$
Answer:
$2.15$