as part of change management, who is responsible for implementing approved change requests?\nteam…

as part of change management, who is responsible for implementing approved change requests?\nteam member\nproject manager\nproject sponsor\nchange control board

as part of change management, who is responsible for implementing approved change requests?\nteam member\nproject manager\nproject sponsor\nchange control board

Answer

Brief Explanations:

In change management, team members are tasked with implementing approved change requests as they are the ones doing the actual work on the project. The project manager oversees and coordinates, the project sponsor provides funding and high - level support, and the change control board reviews and approves changes.

Answer:

Team member