posttest\nthe project management department in your company organizes work across all departments and makes…

posttest\nthe project management department in your company organizes work across all departments and makes the schedules that departments must follow. the project managers researched and purchased a new scheduling tool. the reports generated by the tool are not useful to the other departments, and they cannot follow the schedule.\nwhich is the best way to handle the situation and which is the worst way to handle the situation?\n1. form a team of representatives from every department to research scheduling tools.\n2. have the project managers find a new tool that is useful for everyone.\n3. continue to use the new tool and let the other departments make their own schedules.\n4. require each department to explain exactly why the reports are not useful.\nselect one best answer and one worst answer below.\nwhich is the best way to handle the situation?\noption 1\noption 2\noption 3\noption 4\nwhich is the worst way to handle the situation?\noption 1\noption 2\noption 3\noption 4\nsubmit

posttest\nthe project management department in your company organizes work across all departments and makes the schedules that departments must follow. the project managers researched and purchased a new scheduling tool. the reports generated by the tool are not useful to the other departments, and they cannot follow the schedule.\nwhich is the best way to handle the situation and which is the worst way to handle the situation?\n1. form a team of representatives from every department to research scheduling tools.\n2. have the project managers find a new tool that is useful for everyone.\n3. continue to use the new tool and let the other departments make their own schedules.\n4. require each department to explain exactly why the reports are not useful.\nselect one best answer and one worst answer below.\nwhich is the best way to handle the situation?\noption 1\noption 2\noption 3\noption 4\nwhich is the worst way to handle the situation?\noption 1\noption 2\noption 3\noption 4\nsubmit

Answer

Brief Explanations:

The best approach involves getting input from all departments to find a useful tool, which is Option 1. The worst approach is to continue using a non - useful tool and make other departments create their own schedules, which is Option 3. Option 2 only involves project managers and may not consider all departments' needs. Option 4 is a good step in understanding the problem but not the best overall solution.

Answer:

Best answer: Option 1 Worst answer: Option 3