in a predictive project, which stakeholder has the final authority on whether project requirements have been…

in a predictive project, which stakeholder has the final authority on whether project requirements have been met? project manager manager customer project sponsor
Answer
Brief Explanations:
In a predictive project, the customer is the one who defines the requirements and has the final authority to determine if those requirements are met, as the project's output is for the customer's use or satisfaction. The project manager oversees execution, the project sponsor provides funding/support, and "Manager" is too vague.
Answer:
Customer (from the option list: Customer)