problem 1 - project network\ndraw a project network from the following information.\nwhat activity(ies) is a…

problem 1 - project network\ndraw a project network from the following information.\nwhat activity(ies) is a merge activity?\nwhat activity(ies) is a burst activity?\nid\ta\tb\tc\td\te\tf\tg\th\ndescription\tidentify topic\tresearch topic\tdraft paper\tedit paper\tcreate graphics\treferences\tproof of paper\tsubmit paper\npredecessor\tnone\ta\tb\tc\tc\tc\td,e,f\tg

problem 1 - project network\ndraw a project network from the following information.\nwhat activity(ies) is a merge activity?\nwhat activity(ies) is a burst activity?\nid\ta\tb\tc\td\te\tf\tg\th\ndescription\tidentify topic\tresearch topic\tdraft paper\tedit paper\tcreate graphics\treferences\tproof of paper\tsubmit paper\npredecessor\tnone\ta\tb\tc\tc\tc\td,e,f\tg

Answer

Explanation:

Step1: Understand merge and burst activities

A merge activity has multiple predecessors, and a burst activity has multiple successors. Analyze the predecessor - successor relationships from the table.

Step2: Identify merge activities

Activity G has predecessors D, E, F, so it is a merge activity.

Step3: Identify burst activities

No activity in the given table has multiple successors, so there are no burst activities.

Answer:

Merge activity: G; Burst activity: None