problem 1 - project network\ndraw a project network from the following information. what activity(ies) is a…

problem 1 - project network\ndraw a project network from the following information. what activity(ies) is a burst activity? what activity(ies) is a merge activity?\nid description predecessor\na identify topic none\nb research topic a\nc draft paper b\nd edit paper c\ne create graphics c\nf references c\ng proof of paper d,e,f\nh submit paper g\nproblem 2 - aon network times\nthe project information for the custom order project of the air control company is presented here. draw a project network for this project. compute the early and late activity times and slack times. identify the critical path.
Answer
Explanation:
Step1: Define burst and merge activities
A burst activity has more than one immediate - successor, and a merge activity has more than one immediate - predecessor.
Step2: Analyze each activity for burst
Activity C has successors D, E, and F. So, C is a burst activity. Activity A has only one successor B, so it's not a burst activity. Other activities B, D, E, F, G, H also have only one successor each.
Step3: Analyze each activity for merge
Activity G has predecessors D, E, and F. So, G is a merge activity. Other activities A, B, C, D, E, F, H have only one predecessor each.
Step4: Draw the project network
Start with activity A. Connect A to B. Then connect B to C. From C, draw arrows to D, E, and F. Connect D, E, and F to G. Finally, connect G to H.
Answer:
Burst activity: C Merge activity: G