a project manager is building a budget by estimating the cost of each task and then using that to estimate the cost of each deliverable. what kind of budgeting is occurring?\nparametric\nbottom - up\ntop - down\nhistorical

a project manager is building a budget by estimating the cost of each task and then using that to estimate the cost of each deliverable. what kind of budgeting is occurring?\nparametric\nbottom - up\ntop - down\nhistorical

Answer

Brief Explanations:

El presupuestado bottom - up consiste en estimar los costos de las tareas individuales y luego sumarlos para obtener el costo de los entregables y del proyecto en su totalidad. En este caso, el gerente de proyecto está siguiendo este enfoque al estimar el costo de cada tarea primero y luego del entregable.

Answer:

B. Bottom - up