a project manager receives a suggestion for an app feature that was not part of the original development…

a project manager receives a suggestion for an app feature that was not part of the original development scoping. what should be the first step taken to add it to the project scope? do an impact analysis on the change send the changes to the change review board identify a change request make the change to the project scope
Answer
Answer:
Identify a change request