a project manager is trying to decide which approach to take for a project with a defined scope, but the…

a project manager is trying to decide which approach to take for a project with a defined scope, but the scope can change rapidly based on customer feedback. which approach should be used? critical path hybrid predictive adaptive
Answer
Brief Explanations:
The project has a defined scope but can change rapidly. Adaptive approach is suitable for projects with high - uncertainty and rapid - changing requirements. The Critical Path method is for scheduling and identifying the longest sequence of activities. Predictive approach is for well - defined and stable projects. Hybrid combines elements of predictive and adaptive, but since the emphasis is on rapid change here, adaptive is the best fit.
Answer:
Adaptive