which project occurrences are indicative of an adaptive approach? (choose two) a project is set on one…

which project occurrences are indicative of an adaptive approach? (choose two) a project is set on one overall timeline. project requirements can change frequently. project requirements are set during the planning phase of the project. project tasks are done in sprints.
Answer
Brief Explanations:
An adaptive approach in projects allows for flexibility. Frequent - changing requirements mean the project can adapt to new needs. Doing tasks in sprints (as in Agile methodology) is also adaptive as it enables quick responses to changes. A fixed overall timeline and set - in - stone requirements in the planning phase are more indicative of a predictive approach.
Answer:
B. Project requirements can change frequently. D. Project tasks are done in sprints.