which project occurrences are indicative of an adaptive approach? (choose two)\na project is set on one…

which project occurrences are indicative of an adaptive approach? (choose two)\na project is set on one overall timeline.\nproject requirements can change frequently.\nproject requirements are set during the planning phase of the project.\nproject tasks are done in sprints.
Answer
Brief Explanations:
An adaptive approach in project management is flexible. Frequent - changing requirements allow for adaptability as the project can pivot. Working in sprints also enables quick adjustments based on feedback and changing circumstances. A single overall timeline and fixed requirements in the planning phase are more indicative of a predictive approach.
Answer:
B. Project requirements can change frequently. D. Project tasks are done in sprints.