a project sponsor wants to see a high - level, hierarchical overview of the tasks that need to be completed…

a project sponsor wants to see a high - level, hierarchical overview of the tasks that need to be completed to finish each portion of a project. what document contains this information? project charter rbs wbs project scope
Answer
Brief Explanations:
A Work - Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. It provides a high - level, hierarchical overview of tasks for each project portion. The project charter is a high - level document that authorizes the project. RBS (Resource Breakdown Structure) focuses on resources rather than tasks. The project scope defines what is and is not included in the project.
Answer:
C. WBS