a project team is struggling to stay under budget with a gymnasium build. the project manager is offering…

a project team is struggling to stay under budget with a gymnasium build. the project manager is offering team members free gym memberships for a year if it is finished on time and under budget. what type of tactic is being used to get the project back on schedule? accommodating authority motivation problem - solving

a project team is struggling to stay under budget with a gymnasium build. the project manager is offering team members free gym memberships for a year if it is finished on time and under budget. what type of tactic is being used to get the project back on schedule? accommodating authority motivation problem - solving

Answer

Brief Explanations:

The project manager is offering an incentive (free gym memberships) to team - members to get the project back on schedule. This is a form of motivation as it aims to encourage team members to work harder and meet the schedule goals.

Answer:

C. Motivation