question 24 not yet answered marked out of 10.00 flag question an established methodology where projects are…

question 24 not yet answered marked out of 10.00 flag question an established methodology where projects are run in a sequential cycle. defined as the scope of the project, including time and costs, that are necessary to deliver it are determined early in the projects lifecycle as possible. the process of determining all the requirements of a project. there are two main types of project requirements, business and technical requirements. the tool shows the logical relationships between the activities in a project schedule graphically. the sequence of activities that represents the longest path through a project, which determines the shortest possible duration. critical path network logic diagram predictive life cycle traditional plan based requirements gathering
Answer
Brief Explanations:
- Un proyecto que sigue un ciclo secuencial utiliza un enfoque Predictive Life Cycle o Traditional Plan - Based. Pero el término más común es Predictive Life Cycle para un enfoque secuencial.
- Definir el alcance, tiempo y costos tempranamente es característico del enfoque Traditional Plan - Based.
- Determinar los requisitos de un proyecto se llama Requirements Gathering.
- La herramienta que muestra relaciones lógicas en un cronograma de proyecto es un Network Logic Diagram.
- La secuencia de actividades que representa el camino más largo y determina la duración mínima posible es el Critical Path.
Answer:
- Predictive Life Cycle
- Traditional Plan Based
- Requirements Gathering
- Network Logic Diagram
- Critical Path