rose is in charge of advertising a new product launched by her company. she has defined the advertising for…

rose is in charge of advertising a new product launched by her company. she has defined the advertising for this product as an individual project that consists of seven activities. following are the characteristics of these activities:\n|activity|immediate predecessor(s)|activity time(in weeks)|\n|----|----|----|\n|a|none|2|\n|b|none|2|\n|c|a|4|\n|d|b|5|\n|e|c|5|\n|f|d|2|\n|g|e, f|2|\ncalculate the earliest completion time for the project using a gantt chart.\n10 weeks\n11 weeks\n12 weeks\n13 weeks
Answer
Explanation:
Step1: Identify parallel - start activities
Activities A and B can start simultaneously as they have no predecessors. A takes 2 weeks and B takes 2 weeks.
Step2: Determine subsequent activities
After A is completed (2 weeks), C starts and takes 4 weeks. After B is completed (2 weeks), D starts and takes 5 weeks.
Step3: Analyze further dependencies
After C is completed (2 + 4=6 weeks), E starts and takes 5 weeks. After D is completed (2 + 5 = 7 weeks), F starts and takes 2 weeks.
Step4: Consider the final activity
Activity G can start when both E and F are completed. E will be completed at 6+5 = 11 weeks and F at 7 + 2=9 weeks. So G starts at 11 weeks and takes 2 weeks.
Step5: Calculate the total time
The total time to complete the project is 11+2=13 weeks.
Answer:
13 weeks