a single machine with a mean process time of 2.5 hours and a scv of 1.0. there are 8 work hours per day…

a single machine with a mean process time of 2.5 hours and a scv of 1.0. there are 8 work hours per day. compute the capacity in jobs per day.\n0.32\n3.2\n8\n2.5
Answer
Explanation:
Step1: Recall capacity formula
Capacity = $\frac{\text{Available work - hours per day}}{\text{Mean process time per job}}$
Step2: Substitute values
Available work - hours per day = 8, Mean process time per job = 2.5 hours. So, Capacity = $\frac{8}{2.5}=3.2$ jobs per day
Answer:
3.2