a software development project has had many aspects added that were not approved, nor were they presented to…

a software development project has had many aspects added that were not approved, nor were they presented to a change - control board. as a result, the project will be longer and there is an aggregate risk it will not be done on time. what has taken place in the project?\n\nslipping\n\nproduct backlog\n\ngold plating\n\nscope creep
Answer
Brief Explanations:
Scope creep occurs when additional features or work are added to a project without proper approval or going through the change - control process, which is what happened here as new aspects were added without approval or presentation to the change control board.
Answer:
D. Scope Creep