which stakeholders are initially responsible for reporting the completion of project tasks?\nproject…

which stakeholders are initially responsible for reporting the completion of project tasks?\nproject managers\nteam members\nmanagers\nproject sponsors
Answer
Answer:
B. Team members
Brief Explanation:
Team members execute tasks directly and are first - hand aware when they are completed, so they are initially responsible for reporting task completion.