starbright manufactures child car seats, strollers, and baby swings. starbrights manufacturing costs are…

starbright manufactures child car seats, strollers, and baby swings. starbrights manufacturing costs are budgeted as follows. factory utilities: $85,000 factory foremen salaries: $87,000 machinery setup costs: $31,000 total manufacturing overhead: $203,000 the company uses activity - based costing to allocate its manufacturing overhead costs to products based on the following schedule: overhead cost allocation base estimated activity level factory utilities direct labor - hours 14,580 factory foremen salaries machine hours 17,200 setup costs number of production runs 146 during the current month, the following levels of activities were incurred: car seats strollers baby swings total direct labor costs $ 46,410 $ 79,275 $ 27,405 $ 153,090 direct labor hours 4,420 7,550 2,610 14,580 machine hours 5,500 8,200 3,500 17,200 production runs 40 64 42 146 units produced 1,200 3,100 990 5,290 what are the setup costs allocated to strollers during the current month? note: do not round intermediate calculations. round your answer to the nearest dollar.
Answer
Explanation:
Step1: Calcular la tasa de asignación de costos de configuración
La tasa de asignación de costos de configuración = Costo total de configuración / Número total de corridas de producción La tasa de asignación de costos de configuración = $\frac{31000}{146}$
Step2: Calcular los costos de configuración asignados a los carritos de paseo
Los costos de configuración asignados a los carritos de paseo = Tasa de asignación de costos de configuración × Número de corridas de producción de carritos de paseo Los costos de configuración asignados a los carritos de paseo = $\frac{31000}{146}×64$ Los costos de configuración asignados a los carritos de paseo = $\frac{1984000}{146}\approx13590$
Answer:
$13590$