using the same cost and time estimates, consider the time - effectiveness of each engineer. if scitech is…

using the same cost and time estimates, consider the time - effectiveness of each engineer. if scitech is most concerned about meeting a deadline regardless of the cost, which engineer should the company choose? cost per hour time to complete job camilla $40 20 hours john $30 30 hours nora $20 40 hours oracio $15 50 hours camilla john nora oracio
Answer
Explanation:
Step1: Identify the key - factor
The company wants to meet the deadline, so we focus on the time to complete the job.
Step2: Compare the times
Camilla takes 20 hours, John takes 30 hours, Nora takes 40 hours, and Oracio takes 50 hours.
Answer:
Camilla