what is the work breakdown structure (wbs) as defined by the project management institute (pmi)? a graphical…

what is the work breakdown structure (wbs) as defined by the project management institute (pmi)? a graphical representation of the project budget a task - oriented hierarchical list of all the resources required for a project a timeline that details all the tasks needed for a project completion a deliverable - oriented hierarchical decomposition of the work to be executed by the project team
Answer
Brief Explanations:
The Work - Breakdown Structure (WBS) defined by the Project Management Institute (PMI) is a deliverable - oriented hierarchical decomposition of the work to be executed by the project team. It breaks down the project into smaller, more manageable components.
Answer:
A deliverable - oriented hierarchical decomposition of the work to be executed by the project team