you are a manager observing a spindle - carrier process. it normally takes 3 hours to adjust the speeds and…

you are a manager observing a spindle - carrier process. it normally takes 3 hours to adjust the speeds and temperatures, and it takes 8 hours to conduct the test. how many hours does the process take altogether?\na. 3\nb. 5\nc. 6\nd. 8\ne. 11
Answer
Explanation:
Step1: Identify tasks' times
Adjusting takes 3 hours and testing takes 8 hours.
Step2: Calculate total time
Add the two - times together: $3 + 8=11$.
Answer:
E. 11