assuming a task is on the critical path, what can change to affect the path? (choose two)\nstart date\nend…

assuming a task is on the critical path, what can change to affect the path? (choose two)\nstart date\nend date\nwork hours\nnumber of resources

assuming a task is on the critical path, what can change to affect the path? (choose two)\nstart date\nend date\nwork hours\nnumber of resources

Answer

Brief Explanations:

The critical path is determined by the longest sequence of tasks in a project schedule. The start date and end date directly impact the overall timeline of the project. If the start date of a task on the critical path is delayed, it will push back the entire project. Similarly, if the end date (i.e., the duration of the task) is extended, it will also affect the critical path. Work hours and number of resources can be adjusted (e.g., adding more resources or working overtime) without necessarily changing the critical path as long as the task duration (end date - start date) remains the same.

Answer:

Start date, End date