after completing task 11, the finishing department must wait at least 2 days before beginning task 1.2…

after completing task 11, the finishing department must wait at least 2 days before beginning task 1.2. which of the following does this scenario best describe? a.) lag time b.) lead time c.) average time d.) overall time

after completing task 11, the finishing department must wait at least 2 days before beginning task 1.2. which of the following does this scenario best describe? a.) lag time b.) lead time c.) average time d.) overall time

Answer

Brief Explanations:

Lag time is the waiting time between tasks. Here, after Task 11, the finishing department waits 2 days before Task 1.2, which matches lag time. Lead time is about accelerating, average time is a mean, and overall time is total duration—none fit as well as lag time.

Answer:

a.) Lag time