after completing task 11, the finishing department must wait at least 2 days before beginning task 1.2…

after completing task 11, the finishing department must wait at least 2 days before beginning task 1.2. which of the following does this scenario best describe? a.) lag time b.) lead time c.) average time d.) overall time
Answer
Brief Explanations:
Lag time is the waiting time between tasks. Here, after Task 11, the finishing department waits 2 days before Task 1.2, which matches lag time. Lead time is about accelerating, average time is a mean, and overall time is total duration—none fit as well as lag time.
Answer:
a.) Lag time