which of the following must be done before operating a crane? select all that apply. barricading areas…

which of the following must be done before operating a crane? select all that apply. barricading areas within the swing radius contacting power line owners leveling the crane making other personnel aware of hoisting activities

which of the following must be done before operating a crane? select all that apply. barricading areas within the swing radius contacting power line owners leveling the crane making other personnel aware of hoisting activities

Answer

Brief Explanations:

Barricading areas within the swing radius prevents accidents from objects or people entering the dangerous zone. Contacting power - line owners is crucial to avoid electrical hazards. Leveling the crane ensures stability during operation. Making other personnel aware of hoisting activities helps in coordinating and preventing unexpected interference.

Answer:

Barricading areas within the swing radius, Contacting power line owners, Leveling the crane, Making other personnel aware of hoisting activities