which of the following is a key activity found in phase 1 of the project?\na.) creating a work breakdown…

which of the following is a key activity found in phase 1 of the project?\na.) creating a work breakdown structure after scoping the new project\nb.) deciding not to close the current project and instead working to quickly resolve an identified issue and closely monitor deliverable completion\nc.) closing the project since all project work is complete\nd.) gathering expectations for implementing a new feature on a deliverable to occur in 6 months
Answer
Brief Explanations:
To determine the key activity in Phase 1 (project initiation/definition), we analyze each option:
- Option a: Creating a work breakdown structure (WBS) is part of planning (Phase 2), not Phase 1.
- Option b: Resolving issues and monitoring deliverables are part of execution/monitoring (not Phase 1).
- Option c: Closing the project is Phase 4, not Phase 1.
- Option d: Gathering expectations for a new feature aligns with Phase 1 (defining project scope/requirements, understanding stakeholder needs).
Answer:
d. Gathering expectations for implementing a new feature on a deliverable to occur in 6 months