which of the following situations would be monitored based on the project schedule?\na.) one of the…

which of the following situations would be monitored based on the project schedule?\na.) one of the student’s parents notifies lisa the hotel on campus has no more rooms available for parents to book\nb.) the shop that makes the awards wants their company logo on the wooden plaque, but this goes against school policy\nc.) the dean tells lisa that the budget for the banquet has been reduced, due to a miscalculation.\nd.) lisa is told the invite printing will be delayed by 6 days due to equipment problems at the print shop
Answer
Brief Explanations:
To determine which situation is monitored by the project schedule, we analyze each option:
- Option a: Hotel room availability is a resource/booking issue, not schedule - related.
- Option b: Logo policy violation is a scope/quality issue, not schedule - related.
- Option c: Budget reduction is a cost issue, not schedule - related.
- Option d: A 6 - day delay in invite printing directly impacts the project's timeline, so it is monitored by the project schedule.
Answer:
d. Lisa is told the invite printing will be delayed by 6 days due to equipment problems at the print shop