a project manager is tasked with building a wbs. what does a wbs contain?\ndeliverables\nstatement of…

a project manager is tasked with building a wbs. what does a wbs contain?\ndeliverables\nstatement of work\ntasks\nscope

a project manager is tasked with building a wbs. what does a wbs contain?\ndeliverables\nstatement of work\ntasks\nscope

Answer

Answer:

Deliverables

Brief Explanations:

A Work - Breakdown Structure (WBS) breaks a project into smaller components and contains deliverables. These are the tangible or intangible items that must be produced to complete the project or part of the project. The statement of work is a broader description of the work to be done, tasks are the individual activities within the WBS, and scope defines the boundaries of the project, but the main content of a WBS is deliverables.