during a project planning session for a playground project, a group of people also want the existing…

during a project planning session for a playground project, a group of people also want the existing blacktop to be repaved, which is not part of the original project plan. adding this will result in a budget increase. what else will be affected as part of the project plan? (choose two)\nscope\nschedule\nnumber of resources\nquality
Answer
Brief Explanations:
- Schedule: Repaving the blacktop will add extra tasks to the project, which will take time and thus affect the project schedule.
- Number of resources: More work (repaving) means more materials (like asphalt), equipment (for paving), and labor (workers) will be needed, so the number of resources is affected.
Answer:
Schedule, Number of resources