question: place the steps for mold preparation in the correct order. a) add an initiator to the gel coat. b)…

question: place the steps for mold preparation in the correct order. a) add an initiator to the gel coat. b) apply mastic tape to the edges of the mold. c) apply the gel coat evenly onto the mold. d) cover the surface of the mold with paste wax. e) wait at least 45 minutes for the gel coat to cure. f) wipe the surface of the mold with a wet sponge. possible answers: of,b,d,a,c,e ob,f,c,a,d,e od,c,a,f,e,b od,a,c,e,f,b

question: place the steps for mold preparation in the correct order. a) add an initiator to the gel coat. b) apply mastic tape to the edges of the mold. c) apply the gel coat evenly onto the mold. d) cover the surface of the mold with paste wax. e) wait at least 45 minutes for the gel coat to cure. f) wipe the surface of the mold with a wet sponge. possible answers: of,b,d,a,c,e ob,f,c,a,d,e od,c,a,f,e,b od,a,c,e,f,b

Answer

Brief Explanations:

First, the mold surface is prepared by covering it with paste wax (D) to act as a release - agent. Then, the gel coat is applied evenly onto the mold (C). An initiator is added to the gel coat (A) to start the curing process. After that, waiting at least 45 minutes for the gel coat to cure (E). Next, the surface of the mold is wiped with a wet sponge (F) to clean any residues. Finally, mastic tape is applied to the edges of the mold (B) for sealing or other purposes.

Answer:

D, C, A, E, F, B