tucker is the construction project manager for a new school building. he measures the projects performance and progress by looking at the planned value, earned value, and actual cost. which method is tucker using to determine the project performance?\na. forecasting\nb. performance review(s)\nc. cost management plan\nd. earned value management
Answer
Brief Explanations:
Earned value management (EVM) uses planned value, earned value, and actual cost to measure project performance and progress. Forecasting is about predicting future project status. Performance reviews are general evaluations. A cost - management plan is a document for cost management, not a method to measure performance using these three values.
Answer:
D. earned value management