instruction: for each option, select the best answer choice. options outline key project risks and…

instruction: for each option, select the best answer choice. options outline key project risks and assumptions a b c rank processes based on factors like impact, ease of change, and number of complaints generated a b c draft a succinct, clear, motivating description of what the improvement will achieve a b c

instruction: for each option, select the best answer choice. options outline key project risks and assumptions a b c rank processes based on factors like impact, ease of change, and number of complaints generated a b c draft a succinct, clear, motivating description of what the improvement will achieve a b c

Answer

Brief Explanations:

  1. Outlining key project risks and assumptions is part of creating a project charter which defines the project boundaries, objectives etc. So for "Outline key project risks and assumptions", the answer is B.
  2. Ranking processes based on impact, ease of change and number of complaints is about using clear - cut criteria to prioritize processes. So for "Rank processes based on factors like impact, ease of change, and number of complaints generated", the answer is C.
  3. Drafting a description of what the improvement will achieve is creating a problem statement which clearly defines the goal of the improvement. So for "Draft a succinct, clear, motivating description of what the improvement will achieve", the answer is A.

Answer:

  1. B. Create a project charter
  2. C. Use clear criteria to determine which process to prioritize
  3. A. Create a problem statement