instruction: for each option, select the best answer choice. options outline key project risks and…

instruction: for each option, select the best answer choice. options outline key project risks and assumptions a b c rank processes based on factors like impact, ease of change, and number of complaints generated a b c draft a succinct, clear, motivating description of what the improvement will achieve a b c
Answer
Brief Explanations:
- Outlining key project risks and assumptions is part of creating a project charter which defines the project boundaries, objectives etc. So for "Outline key project risks and assumptions", the answer is B.
- Ranking processes based on impact, ease of change and number of complaints is about using clear - cut criteria to prioritize processes. So for "Rank processes based on factors like impact, ease of change, and number of complaints generated", the answer is C.
- Drafting a description of what the improvement will achieve is creating a problem statement which clearly defines the goal of the improvement. So for "Draft a succinct, clear, motivating description of what the improvement will achieve", the answer is A.
Answer:
- B. Create a project charter
- C. Use clear criteria to determine which process to prioritize
- A. Create a problem statement