1 multiple choice 5 points a key characteristic of this tool is that ea…

Question

1 multiple choice 5 points a key characteristic of this tool is that each requirement is rigorously tested during the verification process and can be a useful planning tool. by linking it to business and project objectives, it adds business value. which management tool from below could help the team complete the goal above? gantt chart project traceability matrix risk matrix swot analysis

Explanation:

Brief Explanations

The described tool focuses on tracking requirements through verification, linking them to business/project objectives. A Gantt Chart schedules tasks, a Risk Matrix assesses risks, and SWOT Analysis evaluates internal/external factors. Only the Project Traceability Matrix maps requirements to objectives and tracks their verification.

Answer:

B. Project Traceability Matrix