what are the deliverables in a project charter? constraints that may im…

Question

what are the deliverables in a project charter? constraints that may impact the project risks that may impact the project tangible outputs or products produced as part of the project assumptions made in developing the project

Explanation:

Brief Explanations

To determine the deliverables in a project charter, we analyze each option:

  • "Constraints that may impact the project" are limitations, not deliverables.
  • "Risks that may impact the project" are potential issues, not deliverables.
  • "Tangible outputs or products produced as part of the project" fit the definition of deliverables (the tangible or intangible products, results, or capabilities provided by a project).
  • "Assumptions made in developing the project" are factors assumed to be true, not deliverables.

Answer:

Tangible outputs or products produced as part of the project