what are the main elements of a project status update? (choose two)
what is forecast to be completed in the next time period.
what has been completed within a specific time period.
overall progress on all projects in progress.
year - to - date statistics on all projects in progress.
A project status update focuses on the specific project's current state and future plans. It first summarizes work finished in the reporting period, then outlines planned work for the next period. The other options are too broad, covering all projects rather than the single project the update is for.