level scheduling (heijunka)assume:• one assembly line produces a mix of models and option combinations• production plan may call for 1500 sunroofs in the coming month• assume 25 production days in the coming month, 15 hours of production each daywhat is the cycle time needed to achieve the required production of 1500 sunroofs next month?ops221 | operations and strategylean operations | 10numericuse: 0123456789 - . ^ esend answer
Step1: Calculate total production minutes
First, convert total production time to minutes:
Total production hours = $25 \text{ days} \times 15 \text{ hours/day} = 375 \text{ hours}$
Total production minutes = $375 \text{ hours} \times 60 \text{ minutes/hour} = 22500 \text{ minutes}$
Step2: Compute cycle time
Cycle time = $\frac{\text{Total production time}}{\text{Required output}}$
$\text{Cycle time} = \frac{22500 \text{ minutes}}{1500 \text{ sunroofs}}$
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
$15$ minutes per sunroof