QUESTION IMAGE
Question
to build a road, the plan is to build 80 meters per day, which takes 20 days to complete. if it is to be completed 4 days ahead of schedule, then more meters must be built per day compared to the original plan.
Step1: Calculate total project length
Total length = Daily length × Days
$80 \times 20 = 1600$ meters
Step2: Calculate new project duration
New days = Original days -提前天数
$20 - 4 = 16$ days
Step3: Calculate new daily build length
New daily length = $\frac{\text{Total length}}{\text{New days}}$
$\frac{1600}{16} = 100$ meters
Step4: Calculate daily difference
Difference = New daily length - Original daily length
$100 - 80 = 20$ meters
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
20