Question
six months into the project, the project manager at farston sent you a message regarding a parts shortage issue. shipment of 30% of the pipes is delayed due to supply constraint problems with the factory by two months. what could have been done in the requirement gathering & analysis phase to avoid this issue? have a conversation with the farston project manager about sourcing material from multiple vendors use a different vendor to supply all the needed materials
The issue stems from relying on a single supplier leading to delays. In the Requirement Gathering & Analysis phase, proactive planning for supply chain resilience is key. The first option addresses this by establishing multiple vendor sources upfront, while the second option (switching vendors later) is a reactive fix, not a preventive step in the early phase.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
Have a conversation with the Farston Project Manager about sourcing material from multiple vendors