which activity is typically not included in the process of closing a pr…

Question

which activity is typically not included in the process of closing a project? archiving project documents preparing project budget evaluating vendor performance obtaining project sponsor’s sign - off

Explanation:

Brief Explanations

Project closing focuses on wrapping up completed work: archiving records, assessing vendors, and getting sponsor sign-off are all standard closing tasks. Preparing a project budget is done in the planning phase, before project execution begins, so it does not belong to closing activities.

Answer:

Preparing project budget