Sovi.AI - AI Math Tutor

Scan to solve math questions

QUESTION IMAGE

in building a new kitchen for a cafeteria, a stove and the vent above t…

Question

in building a new kitchen for a cafeteria, a stove and the vent above the stove can be worked on simultaneously. the vent above the stove needs to be in place before the stove can be tested as part of its completion. which type of dependency exists between the vent and stove tasks? start - start start - finish finish - finish finish - start

Explanation:

Brief Explanations

A finish-start dependency means one task must finish before another can start (or in this case, reach its testing/completion step). Here, the vent must be fully in place (finished) before the stove can be tested as part of its completion, fitting this dependency type. The ability to work on them simultaneously does not change the critical dependency for the stove's testing step.

Answer:

Finish-start