question # 8 multiple select which two professionals are actively engag…

Question

question # 8
multiple select
which two professionals are actively engaged in the pre - construction and design phase of a major construction project? select all that apply.
□ the architect
□ the project manager
□ the construction supervisor
□ the project engineer

Explanation:

Brief Explanations
  1. Architects lead the design of the project during the pre-construction/design phase, creating blueprints and functional plans.
  2. Project engineers collaborate in this phase to ensure design feasibility, handle technical specifications, and align designs with engineering standards.
  3. Project managers oversee the overall project timeline and coordination but are not core design/pre-construction technical leads, while construction supervisors focus on on-site execution during the active construction phase, not the pre-construction design stage.

Answer:

the architect, the project engineer