1910.147, which step must always be completed before maintenance work b…

Question

1910.147, which step must always be completed before maintenance work begins? a. notify affected employees, isolate energy sources, and apply lock/tag devices b. remove all locks and tags

Explanation:

Brief Explanations

For OSHA standard 1910.147 (Lockout/Tagout), before maintenance, the proper lockout - tagout procedures start with notifying affected employees, isolating energy sources, and applying lock/tag devices. Removing locks/tags is done after maintenance, not before. So option A describes the correct pre - maintenance steps.

Answer:

A. Notify affected employees, isolate energy sources, and apply lock/tag devices