Question
level scheduling (heijunka)
assume:
- one assembly line produces a mix of models and option combinations
- production plan may call for 1500 sunroofs in the coming month
- assume 25 production days in the coming month, 15 hours of production each day
what is the cycle time needed to achieve the required production of 1500 sunroofs next month?
Step1: Calculate total production hours
Total hours = $25 \times 15 = 375$ hours
Step2: Convert hours to minutes
Total minutes = $375 \times 60 = 22500$ minutes
Step3: Compute cycle time
Cycle time = $\frac{\text{Total production time}}{\text{Required output}}$
$\text{Cycle time} = \frac{22500}{1500} = 15$ minutes
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
15 minutes