Question
5 multiple choice 3 points forward traceability in a requirements traceability matrix is used to: assess the cost of the project define the projects goals track the projects timeline map the test cases to requirements
Forward traceability in a Requirements Traceability Matrix tracks how high-level requirements are linked to downstream project elements, such as test cases, to ensure all requirements are validated. The other options relate to project cost, goal definition, and timeline tracking, which are not the purpose of forward traceability.